PPL, DIRIO AND NIUPOWER EXPLORE EXTRA SUPPLY TO EASE PORT MORESBY POWER CUTS
Stacey GAUNEDE | November 28, 2026
PPL, DIRIO AND NIUPOWER EXPLORE EXTRA SUPPLY TO EASE PORT MORESBY POWER CUTS

PNG Power Limited (PPL), Dirio Gas Power Station and NiuPower are working together to explore a potential increase in electricity supply to the Port Moresby grid, as load shedding continues across the capital.

The agreement to investigate the option followed a meeting this week between PPL Acting Chief Executive Officer Noel Mobiha and his team, Dirio Chief Executive Officer James Nelson, and NiuPower Chief Executive Officer Michael Uiari.

Port Moresby’s power shortages have been worsened by dry El Niño conditions, which have reduced hydroelectric generation. Falling water levels at Sirinumu Dam have cut output from PPL’s Rouna 1, 2, 3 and 4 hydro stations, while water levels at Edevu Hydro Dam are also declining.

With less hydro power available, supply to the Port Moresby grid has fallen short of demand, leading PPL to implement load shedding. The discussions focused on ways to add generation in the short term while the utility continues to work on longer-term solutions for the grid.

A key proposal is to connect Dirio’s third gas turbine, GT3, which has a capacity of 15 megawatts. Dirio has three gas turbines with a combined capacity of about 45 megawatts, but the existing 66-kilovolt transmission line used to deliver its power can carry only around 30 megawatts. This limits Dirio to operating two turbines at a time through that line.

Under the configuration being considered, Dirio’s first two turbines would continue supplying the grid through its existing transmission line. GT3 would connect through NiuPower and use the 66-kilovolt line already used by NiuPower to export electricity.

Dirio and NiuPower management agreed to work with PPL to examine the proposal. Technical and operational teams from all three organizations will now assess the details required to bring the additional turbine online. PPL’s National System Operations team has already completed preliminary technical studies.

Speaking after the meeting, Mr. Mobiha thanked both companies for their cooperation during a difficult period for PPL and its customers.

He particularly thanked Mr. Nelson and Mr. Uiari with their teams for standing with PNG Power during this challenging time.

“This understanding between all parties means our technical teams can now move further with exploring this configuration. Once the connection details are confirmed, the 15 megawatts from Dirio’s third gas turbine would add power to the Port Moresby Grid and help reduce load shedding. In the meantime, we are continuing our work on long-term solutions,” Mobiha said.

If the connection is technically and operationally viable, the additional 15 megawatts could help narrow the gap between electricity supply and demand and reduce the frequency or duration of outages. The proposal remains subject to the teams completing their assessments and confirming the connection arrangements.

Load shedding has disrupted households, schools, health facilities and businesses across Port Moresby, underscoring the need for both immediate measures and sustained investment in generation and transmission infrastructure.

PPL thanked customers for their patience and said it would provide updates as work progresses. Customers can follow PNG Power Ltd on Facebook or visit the company’s website for load-shedding information.